Del Valle renovation is back on track, but pool work continues until after Labor Day
By Jeff MathesonDirector of Resident Services
The pool project at Del Valle is finally resuming work. The city of Walnut Creek has issued the required permit and work should resume the first week of August. Rossmoor anticipates the pools will reopen after Labor Day.
A great deal of work is being done with the remodel of the Del Valle Clubhouse. This includes work being done to the pools and the pool operating systems. The work associated with the pools includes replacing the plaster, tile and coping for the two pools and the spa. The work in the pump room includes replacing the three heaters, replacing the existing pumps with high efficiency, replacing the chemical controllers, and adding a new ultra violet secondary sanitation system.
Patrons of the pools will also enjoy new accessible restroom/changing rooms right off the deck, new deck showers, completely remodeled locker rooms, a remodeled lifeguard office and a new entry.
The original plan was to complete the plaster work and the work to the pump room as well as the new deck accessible changing rooms by July 1 so the facility could reopen to residents. A temporary entry through the existing patio area would be used and the construction area would be protected from the public. Unfortunately, the pool work has run into significant delays that have prevented GRF from meeting this original opening date.
Operation of public pools is governed by the County Health Department. The Health Department also must approve and issue a permit for construction or renovation of public pools. In addition, a city building permit must be obtained. The project has received the county health permits; however, securing city building permits has taken additional time.
The original project was approached as maintenance that is required for pools every seven to 10 years and not expected to require significant design or approval. The city code, however, requires that when a facility has improvements that reach a minimum dollar amount that the entire facility must then be brought up to current building code for accessibility. This requirement has added to the scope of the project. Accessibility code deals with items such as entry doors, signage, hand rails, lifts for access into the pools and slope of the concrete deck.
GRF staff is working with consultants, including an accessibility specialist, to evaluate the existing facility. It has been determined that a number of items must be addressed and included in the plans in order to obtain the required building permit. These items include the need to replace sections of the pool deck to meet the requirements for an accessible path of travel to the lifts located at each pool.
Several doors or door hardware must be replaced, signage must be added, additional fire alarm horns and strobes must be added, one of the accessible lifts must be replaced and the handrails must be replaced.
Based on the delay in obtaining the building permit and the additional scope of work, GRF is now anticipating the pools will reopen after Labor Day. Although this has been a time-consuming and frustrating process, the end result will be a facility that is more accessible for all residents.