CEO’s Monthly Report
Del Valle Renovation Status, Road Improvements and Drop Creek Structure
By Tim O’Keefe, CEO
The Fitness Center continues on track for a January re-opening although the renovation project has not been without its unique challenges. Rossmoor acquired the Del Valle pool, gym and locker rooms (also the baseball and football fields which are now Mutuals 56 and 58) in 1984 when the facilities were already 25 years old. Rossmoor did not receive the original blueprints for any of the facilities it acquired. As a result, there have been surprises when the walls, ceilings, roofs and floors have been opened up during the demolition phase.
In addition, the city of Walnut Creek Planning Department has created new demands and additional restrictions before signing off on each subsequent phase of the renovation. There have been some delays and some added costs but the project is still scheduled to be completed on time and on budget.
The pool renovation is in process, albeit with some delays. The replacement of pool plaster, pumps and heaters as well as the installation of the UV filtration system do not require the obtaining of building permits from the city. The only requirement was for us to obtain a permit with the county’s Environmental Health Department. However, when the city inspector saw the workers removing the plaster in the pools when he was at the Fitness Center for an inspection, he insisted on making changes to the accessibility of the pools in order for the pools to be re-opened prior to the completion of the Fitness Center because the pools and Fitness Center share a common wall.
Our architect is in the process of working with the city to create the necessary designs to comply with current standards resulting in a delay in the completion of the pool renovations. More to follow.
Rossmoor Parkway roadway
improvements and Nixle
The roadwork and the striping are finally complete outside the Rossmoor gate. Thanks to everyone for their patience while the city of Walnut Creek completed the project but special thanks to the city for finally improving the roadway. Some residents have wondered why the roadway is not as smooth as a full asphalt replacement. As explained previously, the city did not have funds budgeted for new asphalt and indicated it was not going to budget to replace the roadway outside our gate for several more years due to other more pressing roadway repairs throughout Walnut Creek, particularly on streets with heavier traffic.
Instead, the city agreed to overlay a “cape seal” of emulsified gravel with a couple of layers of slurry. We’re told that a cape seal costs about one-tenth of the cost of a full asphalt replacement and will extend the life of the roadway six to 10 years. While not as nice and smooth as a full asphalt replacement, it is a significant improvement over the previously rutted, chopped and cracked roadway.
If you traveled in/out of Rossmoor on the days the city crews were working, you would have experienced frustrating delays during the lane closures. However, if you had signed up for Nixle – Rossmoor’s emergency notification system – you would have learned about the road closures in advance and avoided the traffic tie-ups. If you would like to receive emergency notifications pertinent to Rossmoor via your phone, text message or email – or all three (!) – then go to www.rossmoor.com and click the link in the box about half way down the home page on the left. There is no cost to join.
Drop creek structure
After more than two years of government agency delays, GRF has received all the necessary permits from the Army Corps of Engineers, San Francisco Bay Regional Water Quality Control Board, Federal and State Departments of Fish and Wildlife, city of Walnut Creek and others. We are finally ready to begin work on the replacement of the failed drop creek structure located in the creek between the gate and Waterford.
Neglecting this item poses risks to Rossmoor Parkway and possibly Waterford should erosion continue unabated in the creek which could result in much more expensive repairs. Unfortunately, with the final approvals coming so late in the summer from the various regulators, the permits require that the work be completed no later than Oct. 15. If not completed by then, the work cannot commence until mid-June 2018 when the creek levels should again be at their lowest.
GRF went out to bid but only one bidder responded. The GRF Board of Directors will be evaluating the bid at the July 27 meeting and determining whether the work should commence now or re-bid next spring in the hope of attracting more bidders. As with any construction project but especially during this very busy time for construction contractors throughout the Bay Area, delays usually add to the cost and there is no assurance that it will be bid any cheaper—or that there would be any more bidders—a year from now. The current bidder has extensive experience with creek restoration projects.
Traffic and pedestrian safety study
The GRF Board last year authorized a traffic and pedestrian safety study as a result of extensive and ongoing feedback from residents that many drivers in the valley pose a risk for others on the road, in the parking lots and on the sidewalk due to unsafe driving and excessive speed. At the July 27 GRF Board meeting, the Board will review the final draft of the safety study prepared by TJKM, traffic engineering consultants. TJKM has monitored vehicle speeds at several locations around the valley, reviewed accident data and made extensive recommendations that they believe will reduce speeds and make the roadways, entries and parking lots safer for drivers and pedestrians. Residents are encouraged to review the study and provide input on the recommendations.
Employee transition
One employee, Amanda Forsland, front desk attendant, Fitness Center, commenced employment with the Golden Rain Foundation in June.
Two employees terminated employment with the Golden Rain Foundation in June: Jose Tinajero, landscape technician, MOD Landscape Department; and Ann Pagliaro, Counseling Services.
One employee, Maria “Lucy” Limon, transferred from Office Aide, Recreation, to Administrative Assistant, MOD, in June.