Mutual 48 solar panels are up and ready, but not yet connected

In print on page 5A

Aerial view of tan townhouse buildings with solar panels on their roofs, surrounded by trees and green hills.
Photo by Ron SchwartzPhoto by Ron Schwartz

The solar panels in Mutual 48 are up, but PG&E has not made the connection, which was originally scheduled for May 30, leaving 24 homes in the Mutual stranded without their solar power to their homes. PG&E has cancelled the solar panel connection to the grid three times.

Many of the subscribers have written to PG&E headquarters and personally contacted their schedulers and the public relations department to complain about not being connected. PG&E recently told the Mutual that it may not be able to make the connection until the end of July.