Repaving outside Rossmoor set to be finished by June 26
By Maggie SharpeStaff writer
Residents entering and exiting Rossmoor through the front gate this week may notice a rougher ride than usual on the four lanes between Rossmoor Parkway and Tice Valley Boulevard as work on resurfacing that stretch of the street continues.
The roadway is receiving two coats of sealing materials, called a “cape seal.” This follows patching of the most failed sections of the road earlier in June. Work is being done on two lanes at a time, so there is always access.
Last Friday, June 16, workers from the city’s contractor, American Pavement Systems, applied the first coat, spreading and machine-rolling loose rubber-coated gravel onto a sticky emulsion base, a process known as “chip seal.”
The chip seal takes 10 days to dry or “cure” -- “just like paint,” said city of Walnut Creek Public Works Director Heather Ballenger. “We want the chips to really embed into the emulsion and make a strong foundation,” she said.
On Monday, June 26, after those 10 days of curing, a second coat called “slurry seal” will be applied on top of the chip seal.
“The slurry seal, an emulsified mixture of oil and sand, adds another element of surface and durability to the road,” said Ballenger, adding that slurry seal work is scheduled to be complete in one day.
The road will be smoothed out and workers will sweep or vacuum loose stones and sand. Temporary striping will be spray-painted to delineate lanes of traffic. Permanent striping will be applied later on.
Rough ride
In the meantime, drivers (and cyclists) may notice loose gravel kicking up from the road. Although workers will “vacuum” regularly during the 10-day curing period, residents should expect a slightly “rocky” ride.
“Loose gravel on the road can kick up into a car’s wheel well or the car behind,” said CEO Tim O’Keefe. “We ask drivers to go more slowly. After 10 days, it won’t be a problem any longer.”
After the slurry seal dries – which takes four or five hours – workers will use a vacuum-style device to clean up remaining bits of gravel. During those four or five hours, no vehicles will be permitted to drive on that portion of roadway.
Ballenger emphasized that, despite some temporary inconvenience, one lane into and out of Rossmoor will remain open at all times, though drivers might experience short delays at the gate.
In addition, personnel at the fire station on Rossmoor Parkway have been alerted about the road work and will have emergency egress from the station 24/7.
“During construction on June 26 (slated for 7 a.m. to 6 p.m.) it will be pretty hectic with a lot of workers and heavy equipment around,” said Ballenger. “We encourage Rossmoor residents to skip Safeway that day and try to avoid going out.”
Cost-effective
Ballenger describes the cape seal as “a cost-effective tool or treatment” that the city regularly utilizes. The current work on Rossmoor Parkway is costing the city about $102,000 – as opposed to about $600,000 for a thick new overlay of asphalt.
“The cape seal is something we’re using throughout the city,” said Ballenger. “It’s a nice tool and stretches city dollars.”
She said the city’s pavement program assesses street conditions every year – but that the city doesn’t have the money to do every needed fix. The city decided to fix Rossmoor Parkway after O’Keefe relayed residents’ complaints about the deteriorated state of the road.
“We usually fall about $4 million short every year, so utilizing the cape seal is a very strategic way to repair the roads,” she said. “The cape seal is much better than just a slurry seal. It’s more cost-effective than a complete overlay, improves rideability, and lasts at least 10 years.”
Ballenger added that slurry seals alone are also an effective way to maintain a road. “If a slurry seal is applied every five to seven years, the oil and sand act to rejuvenate the road and prevent it from cracking,” she said.