Rossmoor News, June 14, 2017

Road work at front gate continues this week

In print on pages 1A and 8A

A tree-lined street with a 'Left Lane Closed Ahead' sign and orange cones, with cars driving past a white building.
News photo by Mike DiCarloNews photo by Mike DiCarlo

The city of Walnut Creek notified Rossmoor one day before it planned on doing patch work on the outgoing lanes of Rossmoor Parkway last Wednesday and Thursday. Now the city plans to do cape seal (repaving) beginning Friday, June 16.

Preliminary preparation, treatment and striping removal will take place prior to Friday–most likely on The city of Walnut Creek’s Department of Public Works surprised Rossmoor last Tuesday and announced it would be doing patch paving on the outbound lane of Rossmoor Parkway from the gate to Tice Valley Boulevard on Wednesday. The paving was supposed to take just one day but lasted until Thursday. A cape seal will be done on the roadway this week.

Thursday, June 15.

The cape seal should extend the life of the roadway by six to eight years and is significantly less expensive than laying a new roadway.

When the contractor puts down the emulsion layer and small-coated gravel on the roadway on Friday, it takes a week-plus to cure. The contractor will then return on June 26 and slurry over the gravel. For 10 days there will be loose gravel kicked up off the road and will require cars to drive slower than normal.

Here is the schedule the city sent Rossmoor:

1. Striping removal will take place prior to next Friday’s chip operations.

2. Chip work will be performed Friday, June 16, in a single shift

3. Slurry work should be performed on Monday, June 26, in a single shift. (Work hours will need to be extended to accommodate.)

4. The road will be cleaned and swept before placing chip.