Timeline calls for renovation of Fitness Center to start in March, reopen January 2018
By Cathy TallynStaff writer

If everything goes according to plan, the renovation of the Fitness Center will start as early as March 20 and the building will reopen in 10 months.
The Fitness Center will be completely shut down during construction and will be replaced in part by two 30- by 60-foot modular buildings, which will be placed in the Del Valle parking lot. Classes will be held where there’s room in the other clubhouses. The Del Valle swimming pools will remain open for the most part.
Plans call for the building to be reconfigured by knocking down walls; eliminating dead space, such as hallways, storage and the catering kitchen; repurposing the Delta and Shasta Rooms; and downsizing the Sierra Room.
“It will have the same footprint as the existing building, but we are gaining significant square footage,” said Jeff Matheson, director of Resident Services.
That means more room for residents, equipment and Fitness Center staff.
For example, instead of one aerobics room, there will be three as well as a small Pilates studio.
The roof will be raised. Windows will be enlarged to let in more natural light. This will give the building a more light and airy feeling, Matheson said.
“The facility will be much more open and not chopped up,” he said.
The project was put out to bid last week with bids due the second week of January. The GRF Board could consider awarding the contract at its mid-month meeting in February.
The money for the renovation will come from the Trust Estate Fund. No budget has been approved by the Board. However, the Board has given a guideline of $10 million. That would include all project costs, including any new equipment and furnishings that will be purchased.
“It’s anticipated the first day of construction will be March 20,” Matheson said. “We hope to reopen Jan. 1, 2018.” He said that the plan is to completely shut down the Fitness Center on March 1 and reopen on March 20 in two modular buildings in the parking lot. “That gives us time to pack up and move,” he said.

The portables will house some of the Fitness Center’s equipment. There won’t be enough room in the two buildings to house all of the equipment.
“We need to slim down on equipment,” he said. But, he said, “We’re going to try to keep as much of the program as possible.”
Rossmoor has contracted with Active Wellness to identify what fitness equipment the renovated Fitness Center should have.
Classes will be offered starting in early March in Rossmoor’s other clubhouses.
“We’re using space everywhere,” Matheson said. “We plan on keeping the same level of classes throughout 2017.” In February, schedules will be published with information on where classes will be located.
Pickelball, played on three courts in the Sierra Room, will move to
three new outdoor pickleball courts at Creekside where the old tennis courts were located. The Sierra Room will be shrunk and will accommodate two regulation-size courts when finished.
The enclosed pools will be kept open as much as possible, Matheson said.
“There will be periods of time when they need to close. The other pools should be open by then,” he said. “We’re also looking into bringing in portable showers and changing rooms.”
Beginning in January, residents will be able to keep informed by going to www.rossmoorfitness.com. There is a link to this site on the Rossmoor site: www.rossmoor.com. Click on the graphic on the home page.