At its meeting on Thursday, Dec. 1, the Golden Rain Board will consider expenditures for the 2017 capital budget and the machinery and equipment budget totaling $1,569,500 to be paid from the Trust Estate Fund. The meeting will be at 9 a.m. in Peacock Hall. The following are some of the items that will be presented to the Board for approval:

Capital expenditures Repave Tice Creek Drive (between Avenida Sevilla and Ptarmigan Drive), Terra Granada Drive (between Entry 21 and Avenida Sevilla).

1. Complete the renovation of the kitchenettes in Multipurpose Rooms 1 and 2.

2. Update the audio visual system in the Las Trampas Room.

3. Construct a permanent structure to cover the food service area in Sportsmen’s Park.

4. With the renovation of the Fitness Center, a new electrical panel will be installed in the pump room. This will create the needed capacity to install the UV system. The UV system will help with air quality inside the covered pool area by eliminating chloramines which is a byproduct of chlorine.

5. Install automatic shades for the Fireside Room.

6. Replace the fencing on the south side of the Rossmoor Community Garden.

7. Remove turf from the center median just past the entry gate on Rossmoor Parkway. Replace turf with new landscape emphasizing drought tolerant plantings and color. Landscape will include new water-efficient irrigation system, up lighting on trees and native plant material.

Machinery and equipment budget

Golden Rain Foundation Vehicles

1. To replace a 1990 vehicle 2. To replace a 1987 vehicle 3. To replace a 2004 vehicle 4. To replace a 1998 vehicle Golf/lawn bowling

5. Replace a fairway mower that was purchased in 2005

6. Replace a bunker rake that was purchased in 2004. Information technology

7. The fiber core switch is the primary switch that splits the incoming fiber optic connection and sends it to all of the main foundation buildings. The fiber optic cable transmits all of our corporate data and voice “Telephone” traffic. This unit is over 15 years old and is need of replacing.

8. This project will convert the current storage of printed document to a digital format. This will enable the staff to search over 500,000 scanned documents to quickly access needed information. This new scanning system would also be the foundation for all digitization of printed documents for all departments allowing us to belter server our customers. The current system relies on temporary help or current staff to manually scan documents to micro fiche. The current volume of documents needing to be scanned is beyond staff’s capability to keep up with the demand. This new system will allow staff to access documents from a computer providing almost instant access to required documents. The implantation of this system will ultimately free up two large rooms currently being used only for storage. The cost is shared between GRF and Mutual Operations. Clubhouse and facilities

9. Historically, one of the two pool heaters at Dollar pool gets replaced every year due to complete failure. The pool heaters at Dollar have a shorter lifespan due to the high temperature of the pool. Mutual Operations

10. To replace a 1984 vehicle 11. To replace a 1991 vehicle 12. To replace a 1991vehicle 13. To replace a 1999 vehicle

14. To replace a 2001 vehicle

15 .Purchase a letter folding inserter machine that will fold up to four different sheets of paper into a single envelope and will also insert a return envelope.

16. Upgrade the large conference room at Mutual Operations.