Rossmoor News, October 19, 2016

GRF Board gives go-ahead to seek bids for $10 million Fitness Center project

By Cathy TallynStaff writer

In print on pages 1A and 14A

An artist's rendering of the Fitness Center entrance, showing a front counter, gym equipment and a glass-walled turnstile area.
An artist’s rendition of the entrance to the Fitness Center. Employees will staff the counter to the left, keeping an eye out for residents who will enter through a “gateless” turn style, center. Residents will probably have a card that will be scanned. If someone enters without using a card, an alarm will sound.

With the decision to call for bids to renovate the Del Valle Fitness Center in one phase, the GRF Board set in motion a 12-month schedule to update the center at a cost of no more than $10 million.

Construction is slated to start in mid-February 2017 and finish in mid-October 2017. The facility would reopen in November 2017.

The pools at Del Valle will stay open during construction. But, the Fitness Center will be closed. Three temporary buildings will be put in the Del Valle parking lot to help house the Fitness Center’s 150 classes and exercise equipment. Space in other clubhouses has already been reserved for classes. There is also the possibility of using space at the adjacent Acalanes Adult Education Center.

Sue DiMaggio Adams and Bob Kelso sit at a draped table in a meeting room, listening.
Fred Ponce, left, project manager, answers board members’ questions while Jeff Matheson, director of resident services, listens. Board members Sue DiMaggio Adams, left, and Bob Kelso listen to the presentation about the renovation plans.News photos by Mike DiCarlo

At last Tuesday’s meeting, the GRF Board approved construction drawings for a more open and airy facility with a more efficient use of space.

“I’m very impressed with what we’ve come up with,” said Les Birdsall, Board president.

Fred Ponce gestures while speaking into a microphone at a lectern, with Jeff Matheson listening beside him.
At left, CEO Tim O’Keefe talked about financing the project. At right, Director Stephen Roath makes a point.

The Board also decided to do the project in one phase, which will save time (two months) and money ($706,000).

The city of Walnut Creek is expected to issue the building permit in the beginning of November. Construction bids will be due from general contractors on Dec. 30. Five contractors are interested in the project. The Board is expected to select the contractor and approve funding at its Jan. 10, 2017 meeting.

The construction cost is estimated at $7.4 million with other expenses, such as $1.2 million for professionals services; $360,000 for fixtures, furnishings and equipment; $207, 0000 for temporary facilities; $136,000 for specialized construction costs; and $654,000 for project contingencies for a total of $9.9 million.

Tim O'Keefe speaks at a lectern with his hands open.
At left, CEO Tim O'Keefe talked about financing the project.

Directors will also consider separately replacing the entry canopy at a cost of $207,000. A second alternate bid is to make improvements to the gymnasium at a cost of $114,000. These improvements include refinishing the floor; replacing the heating, ventilation and air conditioning system; improving the acoustics; and adding some windows.

CEO Tim O’Keefe explained the project will be paid for from the Trust Estate Fund. Rossmoor would take out a $9.15 million loan for 15 years at 5 percent interest.

Stephen Roath gestures with both hands while seated at a table during a meeting.
At right, Director Stephen Roath makes a point.

Conservative calculations show that after the repayment of the loan over 15 years that the fund would still total $23 million in 2032, O’Keefe said.

A consultant will make recommendations on what equipment should be purchased for the Fitness Center.

“Most of our equipment is five-plus years old. The trend is to replace equipment after three years. ... Much of it needs to be replaced,” said Jeff Matheson, director of Resident Services.