Renovation of Fitness Center on track
By Cathy TallynStaff writer

Renovation of Rossmoor’s Aquatics, Sports and Fitness Complex is on target to start early next year and be completed within one year.
Plans call for a reconfigured fitness area with about onethird more space than its current size of 19,200 square feet, bringing it to 27,400 square feet.
“We gain this just by reorganizing the existing space,” said Jeff Matheson, director of Resident Services who is in charge of the project.
The additional space is accomplished by knocking down some interior walls; repurposing the kitchen area, Delta rooms and the Shasta Room; and utilizing space now taken by hallways and closets, among other things.
The roof will be raised over the fitness area and the front of the building will have a wall of windows. There will be one entrance for residents to use for the pools, fitness areas and gym.

The schematic design phase has been completed. Work is now focused on design development, which includes construction documents and alternative design plans, among other things.
The Board approved the hiring of the construction company Pankow to look at construction plans and offer various options along with their costs. The GRF Board has approved project costs not to exceed $10 million.
The consultant will also look at options for the phasing of construction and the purchase of fitness equipment.
“This will help us as far as really knowing what the costs will be,” Matheson said.
“The consultant will give us different scenarios,” Matheson said.

For example, should the building be renovated all at once with portable buildings in the parking lot to house equipment and classes? Or should the work be in phases with classes in clubhouses?
The consultant can also evaluate exercise equipment and make recommendations on what needs to be updated or added.
“We’re trying to accommodate everyone’s interests and needs,” Matheson said.
However, in the gym area, formerly known as the Sierra Room, one of the three pickleball courts will be eliminated so there will be more space for the remaining regulation-size courts. “We’re still looking at options for pickleball,” Matheson said.
It’s expected that the matter of the renovation will come back to the GRF Board in October along with an updated cost estimate.