Slurry seal work begins on June 6
In print on page 5A
The following is the schedule for the slurry seal on Rossmoor streets, weather permitting:
Monday, June 6: Grey Eagle Drive (southbound lane), Foxwood Way, Red Wing Court, Woodwren Court and Shadowhawk Way
Tuesday, June 7: Grey Eagle Drive (northbound lane), Falconwood Court, High Eagle Court, Spotted Owl Court and Quail Hill Court
On both days there will be one-way traffic only on Grey Eagle Drive in southbound direction from Saklan Indian Drive to Terra Granada Drive. Eagle Ridge residents will receive a notice delivered door to door about the schedule.
Wednesday, June 8: Tice Creek Drive (northbound lane) between Stanley Dollar Drive and Golden Rain Road
Thursday, June 9: Tice Creek Drive (southbound lane) between Stanley Dollar Drive and Golden Rain Road
Two-way traffic will remain in place, but drive lanes will be narrow. All entries and side streets will remain accessible;but if not living in that area or having any business there, use Rossmoor Parkway to avoid construction zone.
Friday, June 10: Comstock Drive, Castleberry Lane and Wales Drive
Mutual 65 residents will receive a notice delivered door to door about the schedule.
A small section of the Gateway parking lot will be used for staging. The trucks spreading the slurry seal will need to refill sand, rock and oil there.