There were errors in the article in last week’s News on the remodeling of Multipurpose Room 3.

During the budget approval for 2016, the GRF Board approved $185,000 from the Trust budget for renovations to the Multipurpose Rooms at Gateway. The work currently being done by Davis Home Pros is only a portion of the overall work planed. The company is remodeling the kitchen in Multipurpose Room 3, replacing the flooring, updating the lighting, adding ceiling tiles, replacing the chalkboard and updating the finishes throughout.

Through a separate contract, the sliding glass doors will be replaced with new entry doors and fixed glass. Once this is done, work will move to Multipurpose rooms 1 and 2 to update finishes and paint. The kitchens in 1 and 2 will be done in future years.

No work will be done on the roof for the Multipurpose Rooms as stated in last week’s News, and the cost that was quoted was wrong.