Rossmoor had 38 sales in January 2016 as compared with 51 in January 2015. Thirty-four of the sales paid a Membership Transfer Fee. One non-sale transaction also paid a fee. As of Feb. 18, there have been 31 sales for the month and there are about 87 pending escrows.

Employee transition

In January, one employee, Rigoberto Lemus, custodian, transferred from GRF Trust Operations to GRF Custodial.

El Nino update

While the experts tell us that we still have about two more months to go before getting through the heaviest weather of this El Nino season, the Rossmoor drainage systems have held up well and appear to be working as designed with a minimum of problems.

Solar

The Golden Rain Foundation continues to negotiate with NextEra and Solar Technologies on the solar farm for Rossmoor. NextEra and Solar Technologies have completed the site survey, geotechnical evaluation and preliminary environmental review for the solar farm, which will be located on the north slope of Rockview Drive. GRF is still waiting on final confirmation of PG&E rates. The negotiations with NextEra have been challenging thus far, but GRF remains committed to working diligently on securing the best deal for the Golden Rain Foundation. Since GRF is negotiating a 25-year commitment with the vendor, it is imperative that the contract represents our best long-term interests rather than hurriedly agreeing to a contract for the sake of expediency. GRF remains hopeful that all parties will arrive at a mutually beneficial agreement.

Broadband

The TV cable contract with Comcast expires at the end of this year. The negotiations for a new combined TV and broadband contract have begun with two competing providers, Comcast and Wave. As reported last month, Comcast is the incumbent provider of cable services to Rossmoor and is one of the largest TV and broadband companies in the country. Comcast is also a major content producer with many recognizable brand names in its portfolio including NBC and Universal Studios.

Wave is smaller and serves the northwestern region of the country with TV and broadband services. Wave is not a content producer and instead purchases its programming through a consortium. However, because Wave is smaller and newer, its proposal will likely include the installation of the newest technology.

As technology and viewing habits continue to change with the advent of ultra-high definition TVs and with more broadcasting available on the Internet, the Golden Rain Foundation will work to secure a contract that will meet the needs of the community for the foreseeable future with very fast, reliable broadband service to supplement the TV contract at a reasonable cost.

Gateway updates

The GRF Board has approved hiring a space planner to help determine the best uses of studio space in Gateway. In addition, some renovations to the kitchen and entry in Multi-Purpose Room 3 are expected to commence in late March or April.

Del Valle Fitness Center renovation

Last month, the GRF Board of Directors authorized a Del Valle project scope of up to $10 million to renovate the Fitness Center. ELS Architects has been retained to convene a series of meetings with residents and staff over the next few months to determine the best uses for the space. It is expected that they will have construction drawings ready by this fall, which will incorporate best practices for fitness centers serving the mature adult. The renovation will be paid for with Trust Funds.