Rossmoor News, January 20, 2016

President’s Corner

Moving Forward on the Fitness Center Renovations

By Les Birdsall, GRF president

In print on page 7A

At the Jan. 12 GRF Board meeting, several decisions were made to move Rossmoor closer to renovating the Fitness Center.

1 A list of priorities was confirmed that will be considered when designing the Fitness Center. This list was developed as a result of the many meetings held by the consultants with staff and residents.

2. Designated up to $10 million as the value to be used in developing a design.

3. Designated the design team of ELS Architects and the Sports Management Group to provide a proposal at the Jan. 28 GRF Board meeting. This is the consultant group we have been working with since we began the evaluation process. They have been great to work with and have impeccable credentials, have developed many fitness centers and have experience with adult communities. There is an extensive list of their work, with pictures on their websites at www.sportsmgmt.com/projects/ and http://elsarch.com.

We will now “patiently” wait for their first draft. Residents, staff and Board members will have an opportunity to evaluate and comment before there is a final design. Once a design is approved, working drawings must be developed, permits will be provided and then the package will be submitted for bids.

Until we receive a bid(s), we will have no idea about the cost of the renovation.

Solar

The GRF Board is still negotiating the Purchase Power Agreement for the solar array installation in Rossmoor. Since it will be a 25-year agreement, we must make sure we get it right. However, Solar Technologies is working through the city permit process, finishing the final design and preparing construction plans.

The tentative schedule is to begin construction for the solar array by early summer and have the system operational before the end of 2016.

Broadband

GRF is starting negotiations with Wave and Comcast for a new broadband/cable TV agreement. The Comcast contract expires at the end of 2016. I will give residents updates as soon as the Board is able to share more information on the negotiations.