PG&E work on schedule to be completed this month, News apologizes for misinformation
In print on page 1A
PG&E crews, including helicopters, are back in Rossmoor doing a variety of work, including preparations and pulling the wire, through Nov. 13.
The News apologizes for reporting last week that the helicopter work had been completed. The News misunderstood PG&E’s latest schedule.
The power line upgrade project is on track to be complete later this month, but the schedule is contingent on safe weather conditions.
Permissible work hours are 30 minutes after sunrise and 30 minutes before sunset. Arrival at the construction site is approximately 6:30 to 7 a.m.
Active work typically begins between 7 and 7:30.
PG&E is upgrading 27 miles of power line electric transmission towers between Antioch and Moraga.
PG&E says this work will improve reliability and capacity.
For information on the project, contact Customer Outreach Specialist Denise Conway at 877-207-1245 during business hour or email contracostamoraga@pge.com.