Questions and answers on Del Valle renovations
or to cash flow the project.
Is it possible to make the multipurpose gym larger in the new plan?
The allocation of space is a balancing act. The location of the wall in the concept plan is based on the consultant’s assessment of the required space to serve the broad range of users and interests. It is possible to move the wall and make the multipurpose gym larger; however, the Board would need to consider the tradeoffs.
Could the multipurpose gym have operable doors so the room can be used as indoor – outdoor space?
Yes, the plan includes windows and doors for access to the outdoors. Access control is a consideration that must be addressed during the design phase. A patio area or designed outdoor space is not included in this schematic plan; however, it could be added during the design phase or as a future project.
Has an evaluation of space utilization throughout Rossmoor facilities been done to determine if certain programs can be permanently relocated?
Yes, staff has looked at available space at all the clubhouse facilities. Currently, each room is well utilized for a variety of functions. To move classes or programs would impact other current uses. It is difficult to find openings at other clubhouses for classes needing a regular schedule (for example, Monday, Wednesday and Friday from 10 to 11 a.m.).
Will proposals be sought from other architects for completion of the design and construction documents?
If the Board wishes to proceed with development of a final design and construction documents, it can ask the current consultant for a proposal or it can seek additional proposals.
Will the budget estimates include provisions for unexpected issues discovered with the current building such as structural issue?
Yes, the budget for construction will include a contingency allowance. The current cost estimates include a contingency of 8 percent of the total construction cost. In addition, to avoid surprises, a full evaluation of the building will be completed during the development of final plans and construction documents.
Can portable buildings be used if needed during construction?
Yes, however, the phasing plan allows most activities to remain in the building during renovation. Using existing space will help to manage costs.
Will some existing building systems remain and when will they need to be replaced?
All major mechanical systems are near or past their service life and will be replaced.
Is it more costly to phase a project?
Yes, there are steps in phasing that will increase the overall cost of the project but there are also strategies to reduce those costs. The final design and phasing plan will minimize those costs.
Will loud activities be isolated from other activities?
Yes, acoustics are a high priority. Plans and pricing include acoustic separation and control.
Will the renovation provide more natural daylighting?
Yes, residents identified daylight and views to the outdoors as a priority. The renovation will add windows with shade control. The existing skylights that create unwanted glare would be removed.
Will there be an entry system for greater security?
Yes, all entry for the complex would be through the new lobby. This location would have an access control system.
Is the quiet studio (Shasta Room) larger?
Yes, the proposed plan expands the current Shasta Room from 1,700 square feet to 2,000 square feet. It will have acoustic treatment to make it a “quiet” studio.
Is there storage for the spin bikes?
Yes, the proposed plan includes a new multi-use studio where spin classes will be held. This studio includes a specially designed storage room for the spin bikes when not in use. The new studio will have appropriate flooring for spin classes.