Rossmoor News, September 2, 2015

GRF Board on the move for solar array project

By Wilma MurrayStaff writer

In print on pages 1A and 18A

A projected PowerPoint slide titled Big Changes lists five planned improvements to the Del Valle complex.
The Board was treated to another PowerPoint presentation on Del Valle at its August meeting. This slide explains some of the expected changes the renovation will accomplish.

Solar power for GRF facilities looked a little closer to reality when the GRF Board voted unanimously to approve two related business items at the Aug. 23 meeting.

The first decision set GRF up for using Solar Technologies/NextEra to develop a purchase power agreement (PPA) for a solar array to offset energy costs for GRF facilities. The vendor, one of two being considered, was chosen specifically because of its evident commitment to the community as demonstrated in its work with SolarPowered Rossmoor.

The consultant GRF hired to oversee the solar project, William Golove, also recommended this vendor selection.

Board members were concerned that this decision might bind the Board to a PPA, but Resident Services Director Jeff Matheson explained that there is no agreement yet in place. Approving the vendor does not approve the agreement; rather it approves an exclusive arrangement with that vendor to proceed in creating a PPA.

GRF General Counsel Tony Grafals further clarified. This is a “standstill agreement,” or “an agreement to agree,” he said. It gives Solar Technologies/NextEra the opportunity to be the first to bring an agreement to the table.

The other related Board decision unanimously authorized money from the Trust Fund for continued work on the solar farm project. The $75,000 requested would include $50,000 for the consultant (Golove) and up to $25,000 for potential legal fees.

In the Residents Forum, the chairman of SolarPowered Rossmoor, Brad Waite, told the Board the club has been pleased with the consultant’s services and strongly encouraged approving the recommendations put before the Board. “We think that’s the absolutely right decision,” he said.

Del Valle

The Board was not asked to approve anything regarding the Del Valle Complex renovation but it heard another rendition of the Option A-plus presentation that has been given on several occasions for various community and committee meetings.

Prefacing the presentation, Matheson reminded the Board and community that the renovation process has many steps, with lots of “starts, stops and side trips.” Misinformation gets out to the community through rumors, he said.

Sally Moed speaks at a lectern with her hand raised.
Sally MoedNews photo by Mike DiCarlo

“There’s no shortage of opinions,” Matheson said.

The Board’s job, he said, is to sift through all that has been presented and give staff direction on next steps. To that end, he proposes a Board workshop in October.

The consultant team from the Sports Management Group (SMG) was on hand to give an abbreviated PowerPoint presentation on the Option A-plus phasing and answer questions. SMG President Lauren Livingston explained the phasing and what the overall goals were for the renovation based on community feedback.

After all four phases are complete, Livingston said, the overall effect would be a much more effective use of space, increasing locker room size by 34 percent, the fitness area by 44 percent, the studio space by 117 percent and resident services and support by 110 percent. The multi-use gymnasium area would decrease by 33 percent, she said, but that would be compensated by the expansion of other areas allowing for flexibility of programming.

Director Bob Kelso expressed concern about the cost and how phasing would affect it. Matheson said any cost estimates right now are “very rough” and much more would be known after the next steps when the design comes into play.

Director Sue DiMaggio Adams said phasing makes sense. There are other facilities in the community that may have needs that will draw from the Trust Fund and phasing allows for those needs to be addressed if necessary between phases.

Kelso also brought up the idea of bringing in an established company to renovate and run the Fitness Center to save money and/or the possibility of building an entirely new structure.

Matheson said there were a lot of points to consider in the question of starting from scratch, but most importantly, what additional aspects would the community be asking for that weren’t already addressed in the renovation of the current building?

Livingston said the remodeling would make the building state-of-the-art and, with the renovation, it is an appropriate size that is “more than sufficient for a community of this size.” “What would be the driver for a new facility; what would be gained?” she asked.

Also, combined with the indoor aquatics center, it is much “more exciting” than it would be if the fitness complex was separated from the pool complex.

Elizabeth Knefel reads from papers at a lectern.
Elizabeth KnefelNews photo by Mike DiCarlo

“You have a fabulous asset,” she said. The complex would lose “connection and synergy” with the building of a separate facility, she said.

CEO Warren Salmons said the Board session was for information gathering and no decisions had to be made.

Matheson reminded the Board that there are many opportunities along the way to pull back, if needed. The Board would not be locked in simply by moving forward to the design development phase. The message for the day, he said, was “There’s flexibility throughout the process.”

A list of frequently asked questions about the Del Valle Complex is in this issue of the News and has been added to the Rossmoor.com website along with the schematics and other information about the Del Valle upgrade project.

Residents Forum

Traffic safety was the topic du jour for the lightly attended Residents Forum. Two residents who live near Golden Rain Road talked about the dangers of that wide street and two residents talked about storage pods being parked in the community.

There have been many accidents on Golden Rain Road, Sally Moed said. Some have involved animals but some have also involved residents, with tragic aftermath. She complained that Public Safety didn’t do enough to ensure resident safety, citing an incident when a dead deer created a hazard and the only thing Securitas did was put a cone nearby.

“It’s important for them (Securitas) to be part of our community,” she said.

Elizabeth Knefel piggybacked onto Moed’s statements by addressing the speeding problems. Though the speed limit on Golden Rain Road is 15 mph going up and 25 mph going down, she said, “I rarely see that. It’s like a luge run.”

Bob Kelso sits at the center of the GRF board table flanked by Geri Pyle and Dick Hurley.
GRF Director Bob Kelso, center, expresses concerns over the financing of the Del Valle Complex upgrade while Directors Geri Pyle and Dick Hurley look on.

Knefel recommended speed bumps, better speed indicators and perhaps a stop sign.

“Someone’s going to get killed,” she said. “It’s just a matter of time.”

Carolyn Priest also complained about Public Safety, saying the department isn’t “proactive enough.” Safety in Rossmoor is “a fallacy,” she said. “We need to monitor public safety.”

Her primary concern has to do with pod placement and she wrote a new rule that she delivered to the Board.

John Nutley also spoke at the podium about the need for rules for the pods. “It’s a dangerous thing,” he said.

GRF President Les Birdsall said the Policy Committee is already at work on new rules regarding pods.

Other

The Board also approved money that had already been budgeted for a paving contract. It wasn’t unanimous, however. Director Richard Hurley said he didn’t like that the contract wasn’t sent out to bid again.

Mutual Operations Director Paul Donner assured Hurley that the bid had been vetted through staff the way it always has been and that the vendor, Silicon Valley Paving, has been the lowest bidder for years on various projects. He took exception to Hurley’s insinuation that the process was not adequate. Birdsall told Hurley the process was a separate entity and if he thought there was a problem with it, that should be taken up on another occasion. Hurley voted against the expenditure of $98,000 for street maintenance.

Representatives of the Broadband Group gave the Board an update on their most recent report based on surveys and other information. An additional presentation was given at a community forum the same night. A more detailed follow-up of that information will be available in next week’s News.