Rossmoor News, August 12, 2015

PG&E erects cables, poles along 680

In print on page 7A

PG&E recently erected poles and cables along the 680 corridor in Alamo, which is part of its utility line update project.

PG&E is replacing utility lines crossing over 680 and uses the netting to protect the road and drivers as they stretch new wires.

It’s one of the requirements for doing what is called “reconductoring” on the high-power transmission lines crossing over roads. The poles and netting protect the road and drivers below in case of any mishaps and will be taken down in a few months.

A similar project will occur along Highway 4 on the 27-mile long transmission line between Antioch and Orinda. This will last until next year.