GRF Board gets reality check on Del Valle Complex renovations
Costs higher than expected
By Wilma MurrayStaff writer
In print on pages 1A, 3A and 4A

After GRF Board members listened to a number of speakers in the Residents Forum July 30 request that directors think of the future and “go big” with the Del Valle renovations, the Board was forced into a reality check for itself and consequently for the residents. The dreams of a super renovation are stymied by a factor that is always front and center in Rossmoor: cost.
After seeing a PowerPoint presentation on three conceptual design options that included preliminary cost estimates, the Board was faced with figures that caused some sticker shock. Even the simplest of the suggested renovations (Option A) came with a cost of $8,700,000, and that does not include design, project management, permits and equipment costs. At the higher end (Option C), the price goes up to $14,340,000 before those additional costs.
“These numbers are big,” GRF Treasurer Ken Haley said. “They’re huge.”
Haley said with costs like these, there is no way to begin work on the complex next year.
What residents want
Incorporating what residents most demanded for the Fitness Center and the whole of Del Valle Complex (the now-shortened name for the Del Valle Aquatics, Sports and Fitness Complex), Sports Management Inc. and ELS Architecture and Urban Design put together the three-option package.

Dave Petta, ELS principal architect, told the Board that the main resident requests/ objectives were to have more spacious locker rooms; create additional studio space and increase the size and number of studios; increase fitness floor capacity; and enhance resident services. These objectives were the focus of the redesigns.
All three options had in common the same overall system upgrades: improved ventilation, lighting and acoustics and green/sustainable design technologies. In laying out the space, the architects used planning principles for the space that would open up activities to one another through increased visibility; increase natural daylight and views; maximize ceiling height; and develop any usable outdoor areas for pickleball courts, more fitness, a courtyard and a pool patio.
But efforts to please some could only serve to displease others. To better utilize space and open things up, each option included reducing the indoor pickleball court numbers to two. Options B and C include an additional set of three outdoor pickleball courts behind the building. Option C covers those courts, but only with shade protection, not one that would shelter from rain.
As designed, this would not please the pickleball contingent, who stood up one after another in the Residents Forum and reminded the Board that the sport is growing rapidly and needs more space. And indoor space is preferred.
“Pickleball is an indoor sport,” Dale Reynolds said. He said he was disappointed in the design of outdoor courts not adequately protected from the weather. Without covering, “a lot of money will be spent in vain,” he said, and two indoor courts isn’t enough. “The demand exceeds the supply.”
But GRF President Les Birdsall tried to put things into perspective and said the Board couldn’t let pickleball drive the decisions for the overall renovation. More importantly, the Board needs to evaluate what it can and can’t afford.

“There’s so much enthusiasm built up in the community right now that people are ready to charge,” Haley said, but “we’re talking years, not months.”
The solution may be phasing. Resident Services Director Jeff Matheson said phasing opportunities may cost more in the long run, but there are opportunities to stretch out the costs. (Haley had said increased membership transfer fees should help in the future, but the money isn’t there now.)
Birdsall asked staff to provide a recommendation for how the project could be phased.
CEO Warren Salmons reminded the Board to look back at the Creekside project and how the master plan took three to four years to complete and underwent many configurations. There were many “side trips taken during the design process,” he said.
Salmons told the Board the better it can visualize and focus early, the lower the overall cost will be.
Director Bob Kelso quoted an “old saying” in printing that in a job there are three factors: speed, quality and price. One can have two, but not all three at once. Residents will need to choose which two they want, he said.

“We really need for the residents to understand,” Director Sue Adams said; the Board can’t jump into this without the financial facts.
“We’ve got to find a way to make things better without breaking the bank,” Haley said.
“Let’s narrow things down to where we think we want to go, then ask the Finance Committee to look at it,” Birdsall said.
“A solution will come,” Salmons said. “A solution will emerge.”
Meanwhile, residents may look at the plans on the Rossmoor website, view story boards at Del Valle, attend a workshop and attend the next joint meeting of the Aquatics and Fitness Center Advisory Committees. In August, the Board will be asked to choose a preferred alternative and then hear about phasing.

Other business
The Board was unanimous in its approval of almost everything else on its agenda for the morning, from compensation concerns to rubber stamping fund approval for necessary repairs already underway for the Dollar Clubhouse air-conditioning equipment.
Budget principles and the budget calendar were approved. The Compensation Committee’s recommendations for numbers for employee wage and benefits programs for 2016 were approved.
Also, the Board chose a power purchase agreement (PPA) as the financing option for a potential solar array project designed to help offset energy usage at GRF common facilities.
The other Del Valle business item was to approve the mission statement and key objectives for the Del Valle Complex, but this approval ran into snags when word-smithing got underway.
In the Residents Forum, Mary England asked the Board to remove the “health and wellness” verbiage from the mission statement (and consequently from the key objectives).

“GRF does not need to be in the business of offering ‘health and wellness’ activities or services,” she said. Doing so could require oversight and licensing, she said.
That struck a chord with some Board members.
“It implies competency; it implies a credential,” Director Geri Pyle said.
“I don’t want the liability,” Adams said.
Director Bob Kelso agreed. Having those words in the statement could be “justification down the road for something we don’t want to do,” he said.
Though Matheson and Fitness Center Advisory Committee Chairwoman Claudia Tierney both said the terms health and wellness had such a broad usage and interpretation that both Aquatics and Fitness committees were fine with using them, the Board did not share that comfort level. Both the mission statement and the objectives will go back to the committees for further word-smithing.