Rossmoor News, July 15, 2015

HVAC work gets underway at studios

In print on pages 1A and 11A

The phase 1 work on the heating, ventilation and air conditioning (HVAC) system for the Art Studios, Wood Shop, Lapidary/Jewelry Studio and Billiards Room at Gateway got underway on Monday. Some of the areas will be closed while a new HVAC system is installed.

The Wood Shop and Lapidary/Jewelry Studio are completely closed this week through July 17. The shop and the studio will be open and usable from July 20 through 24, but there will be no air conditioning. The Art Studios will be open this week and next week through July 24, but there will be no air conditioning.

Phase 2 of this project has been approved and will include installing a variable refrigerant flow (VRF) HVAC system in the three Multipurpose rooms and the Sewing and Ceramics studios. A date has not been set for the phase-2 work.

In 2012, the GRF Board authorized $180,000 to replace the HVAC piping serving the five crafts rooms in two buildings and between them and the Gateway complex central mechanical building, which serves these two buildings as well as the other buildings in Gateway complex, except for Peacock Hall.

After evaluation, however, it was determined that a much better approach would be to install a different system for these two buildings and connect the Multipurpose rooms building as well. This approach can eventually lead to abandoning the central mechanical building, allowing heating and cooling systems for each building to operate independently so that all do not have to go off when there is a system problem.

In addition, it was determined that using the VRF HVAC system is expected to produce perhaps a 30 percent energy efficiency.

The GRF Board approved phase 2 in the amount of $160,000 at its May meeting. The money to cover both phases of the HVAC system is from the Trust Estate Fund (not coupon funds). The work is being done by K&S Mechanical.