- PG&E does tower modification in Rossmoor, more tower work tomorrow
- Hillside kitchen back in working order
The page as printed
8A Rossmoor News • June 10, 2015
long, 230 kilovolt transmission power line that connects the Contra Costa Power Plant Substation in Antioch to the Moraga Substation in Orinda. Rossmoor is near the transmission line that is scheduled for improvements.
In April, the GRF Board approved an amended temporary construction and helicopter landing site easement with PG&E for this project. The construction easement is in the vicinity of Shadowhawk Way in Mutual 68 (the Eagle Ridge neighborhood). The easement will terminate six months after the project commences. PG&E will pay GRF $2,000 a month for the easement.
Everyone in Rossmoor will receive a letter giving details of the project and the Rossmoor News will continually update residents on the project.
The scope of PG&E’s work in Rossmoor includes gravel and fabric placement on roads, the helicopter landing zone and pull site, clearing brush as needed, weed abatement, minor tree trimming, installation of temporary fencing as needed and installation of a temporary security gate.
Upon completion of the proj-
ect, PG&E will place hardscape at the top of Shadowhawk Way near the entrance to the fire access road instead of replacing the existing lawn. PG&E will be responsible for repairing any damage to the road resulting from the project.
Construction hours Construction will typically occur from 7 a.m. to 5 p.m. Sunday through Saturday. In some areas, construction hours will be from 6 a.m. to 5 p.m. At times, it will be necessary for work to occur outside of these specified times.
Residents may see PG&E crews working on transmission towers and overhead power lines. Large equipment such as cranes or helicopters will be used. Public space such as roads, parks or trails scheduled to be impacted by the construction will be closed for public safety and signs will be posted during the work.
All PG&E personnel are required to carry valid photo identification and are happy to provide it upon request.
For information on the work, contact Customer Outreach Specialist Denise Conway at 877-207-1245 during business hours or email ContraCostaMoraga@pge.com.
PG&E will begin power line upgrade project in Rossmoor in July or August
Continued from page 1A
News photo by Mike DiCarlo A plastic pipe above the Hillside kitchen broke and caused damage to the kitchen. The repair work was completed last week and the kitchen is now open for business. Hillside kitchen back in working order
The kitchen at Hillside Clubhouse should now be back up and running after water damage closed the facility last month.
A pipe broke directly over the kitchen during the Friday Lunch program on May 22. The pipe was for hot water running from the hot water heater over the kitchen.
By the time the water main was shut off, a significant amount of water had soaked through the ceiling from the attic in the kitchen.
The kitchen has been closed to complete the repair to the pipe and to completely remove and replace the plaster ceiling.
The repair was scheduled to be completed last Wednesday and then crews had to clean up all the dishes, cabinets, ice machine and appliances.
The cost for the repair is around $10,000 and GRF is working with its insurance company to see if any of the work will be covered.
Residents can get information from the Rossmoor website:
www.rossmoor.com.
Photos on this page
- A ceiling-damaged kitchen with a ladder, white cabinets, and a drying fan on the floor. Caption: A plastic pipe above the Hillside kitchen broke and caused damage to the kitchen. The repair work was completed last week and the kitchen is now open for business.