Paving begins in entries and on streets in Rossmoor May 18
Here is the paving schedule
In print on page 3A

The GRF Board approved the paving schedule for 2015 at its April meeting. Streets, entries and parking lots throughout Rossmoor are on the schedule.
The work is scheduled to begin May 18 and will continue through June 10, weather permitting. Silicon Valley Paving will do the work. The cost is expected to be around $311,000, with the funds coming from the operating budget. Residents living in areas affected by the work will receive notices delivered to their door. Emergency services will be informed about this schedule.
Schedule Monday, May 18: Terra Granada Drive Entry 2, road base assessment – entry closed; Ptarmigan Drive Entry 14, header board installation – entry open
Tuesday, May 19: Ptarmigan Drive Entry 14, paving – entry closed Wednesday, May 20: Terra California Drive Entry 5: concrete work – entry open; Saklan Indian Drive Entry 12, concrete work – entry open
Thursday May 21: Terra California Drive Entry 5, concrete work – entry open; Saklan Indian Drive Entry 12, concrete work – entry open
Friday, May 22: Saklan Indian Drive Entry 12, paving – entry closed
Tuesday, May 26: Terra California Drive Entry 5, patch paving – entry open; Cactus Court Entry 2, patch paving – entry open; Rossmoor Parkway Entry 6, patch paving – entry open; Saklan Indian Drive Entry 3, patch paving and drainage work – entry closed; Cactus Court Entry 4, patch paving and drainage work – entry closed
Wednesday, May 27: Pine Knoll Drive entries 5 and 9, paving – entries closed
Thursday, May 28: Pine Knoll Drive Entry 9, paving – entry closed
Friday, May 29: Pine Knoll Drive Entry 4, paving – entry closed; Pine Knoll Drive Entry 6, paving – entry closed
Monday, June 1: Pine Knoll Drive Entry 8, paving – entry closed; Tice Creek Drive Entry 5, concrete work – entry open
Tuesday, June 2: Tice Creek Drive Entry 5, paving – entry closed
Wednesday, June 3: Running Springs Road Entry 7, paving – entry closed
Thursday, June 4: Buckeye parking lot, paving – parking lot closed
Friday, June 5: Tice Creek Drive between Avenida Sevilla and Rossmoor Parkway, paving – road closed, detour in place
Monday, June 8: Pine Knoll Drive, uphill lane between Golden Rain Road and Oakmont Drive, paving – one way traffic only, entries 2, 3, 5, 7 and 7A closed Tuesday, June 9: Pine Knoll Drive, downhill lane between Golden Rain Road and Oakmont Drive, paving – one way traffic: entries 1, 4 and 6 closed
Wednesday, June 10: Terra Granada Drive Entry 2, paving – closed