Rossmoor News, October 15, 2014

TAIL WAS WAGGING THE DOG ON DEL VALLE UPGRADE

Jiayi ZhouGolden Rain Road

In print on page 1B

Even though composed by three renowned residents, the self-assigned Del Valle Fitness Center upgrade sub-committee was not a valid organization. GRF had no rule about authorizing such a team to select architects for GRF projects.

The selection was a reverse-Darwin process. Through three screenings, big, reputable firms were eliminated, resulting in the selection of a one-person studio that registered a home office in a Sierra mountain town. While some of the sub-committee meetings were open to residents, the three critical vote meetings were closed to the public.

According to one member of the sub-committee, the sub-committee was heavily manipulated by a staff member. Actually, the sub-committee was just a tool. After the firm was selected, the sub-committee was eliminated. The staff and architect would dominate the rest of the stages of the project, just like what happened on the Event Center.

The staff didn’t follow established industry processes, but instead reinvented the wheel – first select an architect, then let architect conduct the programming. One resident, an experienced architect who graduated from Harvard, criticized it as “putting the cart before the horse.”

As a matter of cause, the GRF Board rejected such “tail wagging the dog” proposal. However, the damage was already done. The Del Valle upgrading was hence postponed for nearly one year, letting down residents’ pressing expectations. It was also wasted energy, time and money of involved architectural firms, staff and residents.

The process of selecting the inferior and eliminating the superiors created a bad reputation of Rossmoor in the architectural world. Is this the taste of a community that claims to be premier?

Next week, I’ll discuss what to do.